CPF Office Building Complex


Engineering Consulting Services for Mechanical, BMS, Heating, Ventilation and Air Conditioning (HVAC) Controls, Electrical and Low Current Systems:

  • Prepared Engineering Reports for:
  • – Mechanical Systems
    – Electrical Systems
    – HVAC Controls
    – Building Management System (BMS)
    – Fire Alarm and DSO Systems
    – Fan Coil Units
    – Tenant Fit Out Works
    – Integrated Building Commissioning
    – Facility Management
    – Construction Cost and Cost Savings

  • Commissioning of:
  • – Mechanical Systems,
    – Electrical Systems,
    – Building Management System (BMS) and HVAC Controls.

  • Engineering and Consulting Services for the Facility Management:
  • – Prepared Procedure, Operation and Maintenance “O&M” Manual for Mechanical Equipment and Systems
    – Prepared Commissioning Reports and Energy Savings Calculations for the building

 

Completion Date: March 2007
Construction Area: 26 100 m2